Applicable Models:
Bug Fixes
Changes and Restrictions
A. Configure the power limit type as ‘user-defined’ and configure the maximum power as 25W. Example:
(GSM5212P) (Config)#poe power limit user-defined 25000
Or,
B. Configure the power limit type as ‘class-based’ and disable the high power Mode. Example:
(GSM5212P) (Config)#poe power limit class-based
(GSM5212P) (Config)#interface 0/3
(GSM5212P) (Interface 0/3)#no poe high-power
(GSM5212P) (Interface 0/3)#exit
Upgrade procedure
After the Apply button is clicked, the file transfer will start, and followed by writing the new image to the Flash memory. Do not power cycle or reboot the switch before the process is complete and the success message show up as below.
After the successful completion the upgrade, proceed to step #8 to restart the switch.
PumpKIN - http://kin.klever.net/pumpkin/
a. # copy tftp://<tftp server IP address><image name> system:image
b. It will ask for confirm with input data displayed. Hit enter if all parameters look correct.
c. The download should take a minute or two, after that, the code will be checked for possible corruption, if not, it will report firmware successfully upgraded.
d. Reboot the switch by typing "reload" command or power cycle the switch.
Make sure that "All" is selected in 'Reboot Unit No' drop down menu box. If it is shown with some other value like '1', then only unit 1 in the stack will be rebooted, and this may result in stack failure after the stack is rebooted. You may select 'Save prior to reboot' option if you feel there are changes that may not have being saved. Click 'APPLY' button to start the reboot process.
a. # show hardware
Or go to GUI System main page to confirm the switch firmware is the one downloaded.